Milestone number |
Milestone name |
Work package(s) involved |
Lead partner |
Expected delivery date 24 |
Comments |
M1 |
Kick-off meeting and steering meeting |
WP 1, WP 5 |
Cefas |
4 |
Planning meetings. Both held in conjunction with workshop 1 for efficiency. |
M 2 |
Workshop 1 |
WP 1 |
Cefas |
4 |
Workshop held, D1 |
M 3 |
Mid-project steering meeting. Review of regional workshop reports |
WP 2, WP 5 |
Cefas |
9 |
Meeting held. Summary reports reviewed and action taken if required. |
M 4 |
Workshop 2 |
WP 3 |
Cefas, AAU (IFM) |
14 |
Workshop held, D3 |
M 5 |
Steering meeting |
WP 3, WP 5 |
Cefas |
14 |
Held in conjunction with workshop 2 for efficiency |
M6 |
Meeting with commission |
WP 5 |
Cefas |
17 |
Meeting held |